Bridge Pile Foundation Construction Now in Full Swing for Section TJ-03 of the Huaifeng Expressway

2026-04-17 4206 0人评论

Bengbu Release Client News    Recently, as the advance-start section of the entire Huaifeng Expressway, the TJ-03 section has now fully launched bridge pile foundation construction, marking the official start of the project's main works.

This advance section is 11.85 kilometers long and includes two major control projects, the Guohe River Grand Bridge and the Qianhe River Grand Bridge, making it a key part of the entire line's construction. At the construction site, pile drilling equipment is operating smoothly, excavators are assisting with earthwork clearance, and all foundation construction is proceeding in an orderly manner.

According to Jia Hao, site construction manager of the TJ-03 section of the Huaifeng Expressway under Anhui Construction Engineering Water Resources, the project department has optimized the construction plan, increased personnel and equipment input, and implemented simultaneous operations at multiple points. At peak times, more than 1,000 workers and over 300 pieces of various machinery and equipment will be deployed, and standards will be strictly implemented, quality control strengthened, and efforts made to build a high-quality and safe project.

In terms of work safety, the project department strictly implements the work safety responsibility system, strengthens on-site inspections and hazard identification, regularly carries out safety education and training, and firmly builds a safety defense line.

According to reports, the project will organize construction scientifically, rationally allocate machinery and personnel, strictly follow the time nodes, and accelerate construction progress on the premise of ensuring safety and quality, so as to ensure completion of the construction task on schedule and lay a solid foundation for the early opening of the Huaifeng Expressway.

Source: Bengbu News Network